| A Photo Gallery Of the Building Progress
|
Moved on 5/26/05 - From Independence Blvd ... | ... To Oceana East Business Park | 2681 Production Road |
BeachEM's New Home #108 | Production Road - Corner Suites | Before our wall was built |
The first stage of preparing the new facility was to seal the walls at the floor. Then the wiring began for overhead lights, the security system, the wall outlets, and light switches.
The Framing of BeachEM's facility was completed. The material used meets and exceeds building standards for Industrial Code. Note: All studs and ceiling joists are 14 gauge aluminum. All plywood for the flooring is fire-rated.
Framing of Office area | Framing - back view | Office area - Inside View |
Entrance View From Mezz. | Front View from Mezzanine | Natural Gas Heating Unit |
Drywall Complete Back wall |
Entrance to Office Area | Penny takes ride on Lift |
The drywall installation was completed in mid April. All rough-in Inspections (General, Plumbing, Electrical) were completed prior to the start of the drywall process.
The Lift was instrumental in reaching the 19
foot ceilings during electrical installation |
Construction Continues ... | Interior work can start -- Painting Installation of Light fixtures Installation of Plumbing fixtures ... |
BeachEm Moves In .. | Office Area & Mezzanine Stairway | Office Area Entrance |
The drywall installation was completed in mid April. All rough-in Inspections (General, Plumbing, Electrical) were completed prior to the start of the drywall process.
June/July Progress .. |
August and Beyond ... |
|
The back wall of the Office Area - entrance to rest room | Accomplishments in July included - painting and carpeting the office area. Most of the "finishing" process was put on hold while BeachEm focused on our main priority, completing our contract work in a timely manner. | The business is "up and running" in
the new location.
|
|